[TPA01] EPYCK01 Hardware Maintenance

Completed
Scheduled for February 28, 2024 at 12:30 PM – 2:01 PM

Affects

TPA01 (Tampa, FL)
Updates
  • Completed
    February 28, 2024 at 2:01 PM
    Completed
    February 28, 2024 at 2:01 PM

    Maintenance has been completed, all instances are rebooting now.

  • In progress
    February 28, 2024 at 12:30 PM
    In progress
    February 28, 2024 at 12:30 PM
    Maintenance is now in progress
  • Planned
    February 28, 2024 at 12:30 PM
    Planned
    February 28, 2024 at 12:30 PM

    We are planning for a scheduled maintenance on Wednesday, February 28th, between 7:30am and 10am EST. This maintenance will impact all customers on EPYCK01.TPA01. We will be powering off this node in order to upgrade the memory and disk capacity.