Las Vegas Datacenter Maintenance - Saturday September 4th
Scheduled for September 04, 2021 at 7:00 PM – September 05, 2021 at 2:23 AM
Affects
LV01 (Las Vegas, NV)
Under maintenance from 7:00 PM to 2:23 AM
Completed
September 05, 2021 at 2:23 AMCompleted
September 05, 2021 at 2:23 AMMaintenance has completed successfully.
Update
September 04, 2021 at 10:08 PMIn progress
September 04, 2021 at 10:08 PMAll nodes are back online! Maintenance still in progress, so there may be some intermittent downtime, but the core work has been completed.
In progress
September 04, 2021 at 8:50 PMIn progress
September 04, 2021 at 8:50 PMMaintenance is now in progress.
Planned
September 04, 2021 at 7:00 PMPlanned
September 04, 2021 at 7:00 PMWe will be performing datacenter maintenance in our Las Vegas, NV datacenter on Saturday September 4th between 1:00 PM and 5:00 PM PST.
We will be moving our nodes to a new rack now that we have used up all of the existing space in our existing rack.
We expect total downtime of ~ 30 minutes per node.